Using one variable, what time did they finish the float in the problem below?Don, Ric and Mike were in a committee to build a float for the homecoming parade. Each of them thought that he could...

Using one variable, what time did they finish the float in the problem below?

Don, Ric and Mike were in a committee to build a float for the homecoming parade. Each of them thought that he could build it alone in 16 hours. Don started work at 8:00 a.m., Ric at 8:30 a.m. and Mike at 9:00 a.m. What time did they finish the float? (use one variable)

Asked on by spock2

2 Answers | Add Yours

thilina-g's profile pic

thilina-g | College Teacher | (Level 1) Educator

Posted on

Given:

One guy can finish the boat alone in 16 hours.

Don start work at 8.00 am

Ric start work at 8.30 am

Mike at 9.00 am

Required:

The time at when they finished the boat.

Solution:

Let's calculate the amount of work to be done to finish the boat.

The amount of man-hours needed (A man hour is the amount of work a single man can do in an hour)

This work can be done by a single person in 16 hours. Therefore the amount of work, W in man-hours is,

W = 1 x 16 man-hours

W = 16.

 

Now if we assume that the total time consumed by the given working pattern is t, we can derive expressions for each person's work.
The sum of these individual works must be equal to 16.

Amount of work Don did = 1 x time consumed.

At the end of work, Don would have worked all the t amount of hours.

Therefore amount of work Don did = 1 x t = t

In he same manner,

Amount of work Ric did = 1 x (t-0.5) = (t-0.5)

Amount of work Mike did = 1 x (t-1) = (t-1)

The sum of above three must be 16.

t+(t-0.5)+(t-1) = 16

3t-1.5 = 16

t = 17.5/3 hours.

t = 5 hours and 50 minutes

 

Therefore the time taken to finish the boat is 5 hours and 50 minutes.

 

Checking:

Now this time must be greater than the time to finish the boat if all three people worked same t hours together from the beginning. That time would be t'.

t' = 16/3 = 5 hours and 20 minutes.

t = 5 hours and 50 minutes.

So t>t'

Therefore this answer must be correct. To be more precise, we can calculate each person's work and add them together and then check whether they sum up to 16.

The amount of work Don did = 1 x 35/6 = 35/6

The amount of work Ric did = 1 x (35/6 -1/2) = 16/3

The amount of work Mike did = 1 x (35/6 -1) = 29/6

 

The sum of work = 35/6 +16/3+29/6 = 96/6 = 16.


Therefore the answer is correct. It is the same amount of work.

 

The Final Answer:

 

The time needed to finsih the work is 5 minutes 50 minutes. Therefore the time when they finish work is (8.00 + 5 h 50 min) = 13h an 50 mins. Therefore they finish at 1.50 pm.

 

The answer is 1.50 pm.

 

leedygood7's profile pic

leedygood7 | High School Teacher | (Level 2) eNoter

Posted on

It is given that all three people can build a float alone in 16 hours,
meaning that in one hour, each person can build 1/16 of the float

For 8:00am to 8:30am, only one person is building the float.
Therefore, 1/16 X 1/2 = 1/32 is done

For 8:30am to 9:00am, two people are building the float.
Therefore, 1/16 X 2 X 1/2 = 1/16 more work is done

Until 9:00am, 1/32 + 1/16 = 3/32 of the work is done
Left work to be done is 1 - 3/32 = 29/32

From 9:00am, all three people are working, meaning that 1/16 X 3 = 3/16 work can be done in an hour.

After 9:00am, 29/32 X (3/16) = 29/6 hours is needed

29/6  hours = 4 hours and 50 minutes
Therefore, the work is done at 01:50  pm

We’ve answered 318,994 questions. We can answer yours, too.

Ask a question